Every fill run has a start-up window in which the product coming out of the nozzle is not the product in the tank. It usually lasts 20 to 40 units. Buyers who sample from the first carton and buyers who never look at it both get a misleading picture of the batch.
1. Why unit one is different
Before the run, product sits in the hopper, the transfer line and the nozzle body. Those volumes have been at a different temperature from the bulk tank, sometimes overnight. The first units therefore carry product that has had a different thermal history, and in a cream that changes viscosity and fill behaviour.
2. Dead legs hold old product
A transfer line that is not fully drained keeps a plug of the previous batch or of the pre-flush. The plug is small, but it reaches the nozzle first. This is the mechanism behind the occasional off-shade or off-odour jar at the head of a run, and it is the reason a line clearance record matters more than a visual check.
3. Weight settling in the first 20
Fill weight drifts as the piston and the product column reach steady state. The first ten units are typically the widest spread, and by unit 30 the weight is inside a normal band. Setting the filler from the first five units is a common way to put a whole run slightly out of tolerance.
4. First-off retention
Keeping the first units as a first-off sample, labelled with time, line and operator, gives the batch a reference point. If a complaint arrives later, the first-off tells you whether the issue was present at the start or developed during the run. Without it, the investigation starts from zero.
5. Line clearance before start
The check is simple: no previous components, no previous bulk, no leftover labels. What goes wrong is the timing, because the check happens before the bulk arrives and the line then sits. A second confirmation at the moment the first unit is filled costs a minute and closes that gap.
6. When to accept the run
A practical rule is to discard units until three consecutive fills sit within the target band, then start the retained production count from there. On a 3,000-piece run the loss is negligible; on a 100-piece run it has to be planned into the material order rather than discovered at the end. Record the unit number where the run stabilised, because that number is the loss to quote on the next order of the same format.
7. How many rejects are normal
Start-up loss of 20-40 units on a sachet or jar line is ordinary, and a supplier who claims zero is measuring something else. What matters is whether the loss is recorded. An unexplained gap between bulk issued and units packed is a bigger warning sign than the loss itself.
8. The audit question that reveals it
Ask how the first-off sample is stored and for how long, then ask to see the record for a recent batch. A factory that keeps first-off by batch and line answers in seconds. One that keeps a single shelf of unlabelled jars answers with a tour. The follow-up question is what the first-off is compared against, because a sample with no reference panel is storage rather than a control.
9. What this means for a buyer
Do not judge a batch from the first carton, and do not let a supplier judge it that way either. Ask for the sample to be drawn after start-up stabilises, and ask for the first-off to be retained. Both requests are standard and both are cheap to meet.
10. Where it fits
Formats that run on these lines, with lead times of 25-35 days after artwork sign-off, are under the product catalogue, production notes and the encyclopedia.