Key takeaways
- The window runs from artwork sign-off, not from the purchase order date.
- A custom base is the stage most likely to run long; ask whether the base is on file.
- Bulk compounding and QC release take days and must finish before filling starts.
- Custom jars, caps or print are a parallel critical path, not a task on the main one.
- Stock-base samples take about 7-10 days and are the cheapest week to compress.
Lead time is quoted as one number and consumed as four. On this catalogue the figure is 25-35 days after artwork sign-off, and buyers routinely ask for 15 without knowing which stage they are asking to shorten. The stages have different costs and different owners.
1. The clock starts at artwork, not at order
Artwork sign-off fixes the print, the dieline and the label text. Before that point the order cannot be scheduled, because the components are not released. Buyers who count the lead time from purchase order date build a week of optimism into the plan.
2. Raw material availability
A stock base means the bulk can be made as soon as the tank is free. A custom base means at least one raw material is ordered for the run, and that is the stage most likely to run long. Asking whether the base is on file is the single most useful question in a lead time conversation.
3. Bulk manufacture and QC release
Compounding, homogenising, cooling and a QC check on the bulk typically take two to four days for a cream or lotion. The bulk cannot be filled until it is released, so a failed viscosity check adds a rework loop that costs another day or two and is invisible in the original quote. A second check on pH and appearance adds hours rather than days, and is worth scheduling into the plan instead of treating as slack.
4. Filling, sealing and packing
This is where volume dominates. A 3,000-piece sachet run and a 30,000-piece run do not take proportionally different setup time, which is why the middle of the range is the most efficient place to be. Packing into shippers and palletising add a day at the end, and both depend on the shipper, the carton label and the pallet pattern agreed with the forwarder before the run rather than during it.
5. Components are the hidden path
Jars, caps, sachet film and cartons arrive on their own schedules. A stock jar is days away; a custom-coloured jar with a printed cap has its own lead time that can exceed the fill. Any component with a custom colour, a new mould or a print is a parallel critical path, not a task on the main one.
6. Where 7-10 days saves a launch
Stock-base samples are filled in about 7-10 days, and a custom development sample usually takes 10-15. That window is the one a brand can compress by choosing a stock base and limiting the changes to colour, fragrance and claims. It is the cheapest week in the whole project.
7. What a rush order really buys
Expediting usually moves the order ahead in a queue and pays for air freight from Guangzhou. It does not shorten compounding, QC release or a stability window. A buyer paying for expedite on a custom base with a custom jar is often paying twice for a saving that only exists in one stage.
8. Planning backwards from a shelf date
Take the shelf date, subtract shipping, subtract packing, subtract the 25-35 day window, subtract sampling and artwork. What remains is the date the brief has to be final. Most late launches are lost at the brief, months before anyone looks at a fill line.
9. The questions that shorten it
Is the base on file. Is the jar stock or moulded. Is the print digital or cylinder. Is the destination served by Nansha or Shekou. Four answers, and the lead time stops being a single opaque number and becomes a plan with levers.
10. Where it fits
Formats with the 25-35 day window stated on the page, plus port of loading, are under the product catalogue, production notes and body lotion formats.
Reference: Production planning notes, 2025